An ADU final walkthrough is the visit near the end of construction where you and your builder walk the finished home together and write down anything that still needs adjusting, finishing or fixing. A list of touch-ups at this stage is normal, not a sign that something went wrong. What matters is that the list is written, agreed, scheduled and completed before the last payment and move-in.

This guide explains how experienced ADU builders plan the walkthrough, what to look at, how it relates to the final inspection, and how to close out the project cleanly.

What an ADU final walkthrough is (and is not)

The walkthrough is a quality review between you and your builder. It is separate from the building department's final inspection:

  • The final inspection is done by the building department or an approved inspector. It checks that the work meets the approved plans and the adopted codes. Passing it is usually what leads to a certificate of occupancy or final sign-off, though the name and process vary by jurisdiction.
  • The final walkthrough covers fit and finish, function and anything in the contract that an inspector does not check, such as paint touch-ups, cabinet alignment, cleaning and agreed selections.

A home can pass inspection and still need a few walkthrough items, and a walkthrough can happen before or after the final inspection depending on the builder's process. Ask your builder how they sequence the two.

Why a punch list is a normal part of the build

The punch list, the written list of items from the walkthrough, is a standard part of finishing any home. After many trades have worked in a small space, small things show up: a door that needs adjusting, a scuff on fresh paint, a caulk line to redo, a cabinet door slightly out of line.

On the ADUs we build, the walkthrough is put on the schedule from the start, along with time to finish the list. Planning for it this way keeps the end of the project calm. When nobody expects a list, the last few weeks can feel tense. When everyone does, it is just another scheduled step.

When to schedule the final walkthrough

A good time is when the work is substantially complete: finishes are in, fixtures are installed, the home has been cleaned and utilities are on so everything can be tested. Walking too early creates a list of items that are simply unfinished, which makes the list hard to track.

Plan for:

  • The walkthrough itself, usually with the builder or project lead present.
  • Time to complete the list, which depends on what is on it and on any parts that need ordering.
  • A follow-up check to confirm items are done.

Ask early how the walkthrough is scheduled and how long the builder usually needs to close out a list.

What to check on an ADU final walkthrough

Bring the plans, your selections and a phone for photos. Then go room by room, inside and out.

Doors, windows and hardware

  • Doors open, close and latch without sticking; locks work and keys are provided.
  • Windows open, close and lock; screens are in place.

Finishes

  • Paint is complete, with no missed spots or drips.
  • Flooring is clean and undamaged, with transitions finished.
  • Countertops, backsplash, tile and grout are complete; caulk is neat at tubs, showers and counters.
  • Cabinet doors and drawers line up and close properly.

Plumbing

  • Every faucet runs hot and cold; drains empty without gurgling or slow draining.
  • Toilets flush and refill properly; no leaks under sinks.
  • The water heater is labeled and accessible.

Electrical and safety

  • Every light, switch and outlet works; the panel is labeled.
  • Smoke and carbon monoxide alarms are installed where required and sound when tested. The U.S. Fire Administration's smoke alarm guidance is a helpful reference.
  • Exhaust fans in bathrooms and the kitchen run.

Heating, cooling and appliances

  • Heating and cooling run and controls work.
  • Appliances are installed, run and match your selections.

Outside

  • Grading slopes away from the ADU, and gutters and downspouts drain away from the foundation where installed.
  • Walkways, steps and landings are finished and safe.
  • The site is cleaned up, and any damage to the yard, fences or the main house is noted.
The complete guide · $129

The Age-in-Place ADU Guide

Design a home around the life your parent wants to keep, build it so it holds up as needs change, and pay no more than it should cost.

How to write a punch list your builder can act on

A clear list gets finished faster. Good habits:

  • Be specific. "Bedroom door rubs at top corner" is easier to fix than "doors need work."
  • Note the location by room and wall.
  • Take photos and share them with the list.
  • Agree on the list in writing before the walkthrough ends, so both sides work from the same version.
  • Separate new requests from punch items. Something that was never in the contract, such as an added outlet or a different fixture, is a change, not a punch item. Handle it as a written change order with its price.

Closing out the project: payment, documents and warranty

How the final payment relates to the punch list is set by your contract, and contract terms and lien rules vary by state. Read the payment section before the walkthrough so you know what triggers the final payment and whether any amount is held until the list is done.

Before or at close-out, ask for:

  • Final inspection sign-off or certificate of occupancy, as your jurisdiction issues it.
  • Warranty information, including what is covered, for how long and how to request service.
  • Manuals and product information for appliances, the water heater, heating and cooling and other equipment.
  • Lien releases, where your state uses them, showing subcontractors and suppliers have been paid.
  • A list of finish selections, such as paint colors, so future touch-ups match.

The National Association of Home Builders consumer resources offer general guidance on working with builders and on home warranties. Specific rules for contracts, liens and warranties change based on jurisdiction, so confirm details locally.

Plan the ending before you start

The smoothest close-outs are planned before the contract is signed. Ask your builder how they handle the walkthrough, the punch list, the final payment and warranty requests. If you are still early in the process, a free ADU lot check helps you understand your site before you design, and the ADU feasibility checklist covers what to confirm before calling a builder. If the ADU will be rented, the ADU ROI calculator can help you plan the numbers for after move-in.