A good ADU construction contract says exactly what will be built, from which drawings, for what price, on what schedule, and how changes get approved. Before you sign, check that the drawings named in the contract are the same set going to (or approved by) the building department, that allowances and exclusions are spelled out, and that payments follow completed work. Contract rules vary by state, so confirm local requirements too.
Why the ADU construction contract matters more than the bid
A bid is a price. The contract is the promise. Most disagreements on a build are not about whether the builder is honest; they come from two people reading the same vague sentence differently. An ADU adds its own risks to that: utilities that run across the yard, permit conditions that appear late, and a small house where every inch of the plan has been negotiated.
Experienced builders want a tight contract as much as owners do. A clear scope protects the schedule, the budget and the working relationship.
Match the contract drawings to the permit drawings
This is the single most useful check, and one of the most often skipped. On the ADUs we build, we make sure the contract names the exact drawing set by sheet list and date or revision number, and that it is the same set the building department approved (or will approve).
Here is why it matters. Plans often change during permitting. A plan reviewer may require a larger footing, a fire-rated wall, an extra window for egress, a different smoke alarm location, or a revised utility route. If the contract was priced from an earlier set, the builder priced a different building from the one you are legally allowed to build. That gap turns into change orders.
Ask for:
- A sheet index in the contract, with dates or revision numbers for architectural, structural and any civil or energy sheets.
- A clause for plan-check revisions. If the approved set differs from the priced set, how is the difference priced and approved?
- One current set on site. Builders, subcontractors and inspectors should all work from the approved drawings.
If you have not yet sorted out your survey, site plan and permit set, our guide to ADU site plans, surveys and permit drawings explains how those documents fit together.
Scope, inclusions and exclusions
The scope should describe the whole project, not just the house. For an ADU that usually means:
- Demolition and site preparation, including tree and root removal.
- Foundation, framing, roofing, windows and doors, exterior finishes.
- Mechanical, electrical and plumbing systems, including the water heater and heating and cooling equipment.
- Utility connections: sewer or septic, water, electric service or panel work, gas if any. Say where each connection starts and ends.
- Flatwork, paths, drainage, fencing and landscaping repair, if included.
- Permit fees, utility fees, engineering, surveys and special inspections, with a clear note of who pays each.
Read the exclusions as carefully as the inclusions. Common exclusions include rock or unsuitable soil, utility company work, landscaping, appliances, window coverings and fees charged by agencies. Exclusions are not bad; surprises are.
Allowances, selections and change orders in an ADU construction contract
Allowances are placeholder budgets for items not yet chosen, such as tile, fixtures, lighting or a utility connection whose length is unknown. They are useful when used sparingly. Ask what each allowance assumes and replace as many as you can with real selections or real numbers before signing. Utility allowances in particular are often guesses until someone confirms the connection point and distance.
Selections should be listed by product or specification where possible. Making finish choices before signing is the simplest way to avoid owner-driven changes later.
Change orders should follow a written process: a description of the change, the price, the schedule impact, and signatures from both parties before the work happens. The contract should say how changes are priced (fixed price, cost plus a markup, or unit prices) and whether verbal approvals count. Keep copies of every signed change.
The Age-in-Place ADU Guide
Design a home around the life your parent wants to keep, build it so it holds up as needs change, and pay no more than it should cost.
Payment schedule, schedule and warranty
Payments. Consumer guidance from state licensing boards and contractor-licensing associations consistently recommends tying payments to completed work rather than to dates. Some states limit the size of a down payment on home improvement contracts. Rules like these change based on jurisdiction, so check your state's contractor licensing board. If a lender is involved, align the contract's payment milestones with the lender's draw schedule.
Schedule. Ask when the clock starts. On most ADUs the build schedule starts at permit issuance, not at contract signing, because design and permitting take real time. The contract should say what pauses the schedule, such as weather, agency delays, inspection availability or late selections, and how delays are communicated.
Warranty. Get the workmanship warranty in writing, including its length, what it covers, how to request service, and how manufacturer warranties on equipment are handed over. Some states set minimum warranty or disclosure terms for residential construction.
Licenses, insurance and legal terms to confirm
Before signing, verify:
- License. Look up the builder's license with your state or local licensing agency, where one exists, and confirm the license type covers the work.
- Insurance. Ask for current certificates for general liability and, where required, workers' compensation. Ask whether your homeowner's policy needs a builder's risk policy or an endorsement during construction.
- Lien protections. In many states, subcontractors and suppliers can place a lien on your property if they are not paid, even if you paid the builder. Ask how lien releases will be collected with each payment.
- Cancellation rights. Federal and many state rules give a short window to cancel certain contracts signed in your home. Required notices and timing vary.
- Dispute resolution. Know whether disputes go to mediation, arbitration or court, and where.
If anything in the contract is unclear, ask for it in writing or consult a local attorney. A contract is easier to fix before it is signed than after.
What an experienced builder checks before signing
On the ADUs we build, the pre-signing review usually comes down to a short list:
- The lot has been checked for setbacks, utilities and easements. A free ADU lot check is a good first pass.
- The contract names the approved drawing set by sheet and revision.
- Site, utility and fee items are priced separately from the building and assigned to someone.
- Allowances are few, explained and realistic.
- Selections are made, or have firm deadlines.
- The change-order process, payment schedule and schedule start date are written down.
If you are weighing the project's return as well as its cost, run your numbers through the ADU ROI calculator before you commit.