Two ADU quotes for the same floor plan can be tens of thousands of dollars apart, and the difference is rarely the building. On the projects we build, the building itself is the predictable part. The big swings come from the site: utility connections, excavation, foundations on difficult soils, septic, access, and permit and impact fees. If you want to compare ADU bids fairly, separate the building price from the site price first.
This guide shows how an ADU builder reads a quote, so you can compare quotes line by line instead of bottom line to bottom line. Specific fees, utility requirements and permit costs change by jurisdiction, so ask every builder to price your actual lot.
Split every ADU quote into building cost and site cost
Ask each builder to show these two numbers separately:
- Building cost: foundation, framing, roofing, windows and doors, insulation, drywall, plumbing, electrical and HVAC inside the ADU, cabinets, counters, flooring, fixtures and finishes.
- Site cost: excavation and grading, utility trenching and connections (sewer, water, power, gas), septic work where needed, tree and root removal, retaining walls, flatwork, driveway or parking, erosion control, and site restoration.
Then add soft costs: design and engineering, surveys, soils reports, permit and plan-review fees, utility tap or connection fees, and any impact or school fees your jurisdiction charges. Some quotes include these, some don't, and some include only part.
A turnkey ADU price only means something once you know which of these three buckets it covers.
The line items where ADU quotes differ most
Utility connections
"Connect to existing utilities" can mean a 20-foot run or a 200-foot run, a gravity sewer or a pump, a branch off the house panel or a brand-new electric service. Ask each builder:
- Where will the sewer connect, and is it gravity or pumped?
- Will the ADU run off the house panel, or get its own service? Is the existing panel large enough?
- Is gas included, or is the ADU all-electric?
- Who pays the utility company's own charges?
Utility "allowances" are often placeholders. A builder who walked the site and found the connection points will usually price this more accurately, even if the number is higher.
Foundations and soils
A standard slab price assumes ordinary soil. Expansive, sandy or silty soils can call for over-excavation, compaction or an engineered foundation. Ask whether a soils report is included, and what the quote assumes if one isn't.
Septic
On a septic lot, the ADU often needs its own system or an upgrade sized for the bedrooms of both homes. Septic rules vary by county and state, so ask whether the quote includes the design, permit and installation.
Permits and fees
Permit fees, plan-review fees, utility tap fees and impact fees vary widely by jurisdiction, and some cities and counties waive or reduce them for ADUs. Ask whether fees are in the price, estimated, or excluded.
Read the exclusions before the inclusions
The cheapest ADU quote is often the one with the longest exclusions list. Common exclusions to look for:
- Utility trenching beyond a set distance, or utility company charges
- Permit, plan-review, tap and impact fees
- Survey, soils report and engineering
- Tree removal, retaining walls and final grading
- Landscaping, fencing and irrigation repair
- Appliances, window coverings, or appliance installation
- Driveway, parking or flatwork
Treat allowances as unfinished decisions
An allowance is a placeholder for something not yet selected: cabinets, tile, fixtures, appliances, lighting. Ask what each allowance covers (product only, or installed), how it was set, and how overages and credits are handled. Low allowances make a quote look cheaper and turn into change orders later. Before you sign, replace allowances with real selections wherever you can.
The Investor’s ADU Guide
Underwrite the deal honestly, then build a unit tenants choose and stay in — for no more than an ordinary one costs.
A simple matrix to compare ADU bids
| Scope item | Builder A | Builder B | Builder C |
|---|---|---|---|
| Building (as drawn) | Included | Included | Included |
| Excavation and grading | Included | Allowance | Excluded |
| Sewer connection (type and length) | Gravity, 60 ft | Not stated | Allowance |
| Electrical service | New service | House panel | Not stated |
| Permit and tap fees | Estimated | Excluded | Included |
| Finishes | Selected | Allowances | Allowances |
Mark every cell included, allowance, excluded or not stated. Every "not stated" is a question to send back before you compare totals.
Questions an experienced ADU builder will answer without hesitating
- What drawings and site information is this price based on?
- When does the schedule start: at contract signing or at permit issue?
- How are change orders priced and approved?
- What does the payment schedule look like, and how does it line up with completed work and any lender draws?
- What is your experience with ADUs in this specific jurisdiction?
Licensing, insurance and contract requirements change by state and by jurisdiction, so confirm your builder is properly licensed and insured where you live.
Before you request ADU quotes
Builders price uncertainty. The more you resolve before asking for bids, the closer the quotes will be. Run the free ADU lot check to see your lot lines, setbacks and buildable area, work through the ADU feasibility checklist, and give every builder the same plans and site information. For a rental ADU, test the full project cost (building, site and soft costs) in the ADU ROI calculator, not the building price alone.